Parking changes

Northwest Tower construction

Sept. 03 - Pruyn Pavilion parking lot is no longer accessible from the main entrance.  Oct. 03 - Construction is underway. Nov. 03 - Facing Pruyn Pavilion Dec. 03 - A boom crane used to pour the concrete walls stretches over the site. Jan. 04 - Workers erect concrete forms in preparation to construct the foundation wall adjacent to Pruyn Pavilion.  Feb. 04 - In foreground, one of the tower's exterior columns.
March 04 - Third floor nears completion. April 04 - Three floors complete. Three to go. May 04 - Steel is complete. June 04 - Boom crane stretches to supply cement to tower's upper floors. July 04 - View from main parking lot. Aug. 04 - Framing takes shape on tower's first three floors.

Sept. 04 - Paving is complete for the new tower's main entrance.

Oct. 04 - Brickwork and curtain wall nears completion Nov. 04 - Only a few glass panes remain to complete the curtain wall.

Dec. 04 - The tower's exterior view should remain unchanged for the next several months.

Jan. 2005
No photos
available

Feb. 05 - View from Hudson Ave

March 2005
No photos
available

April 05 - Work on the pillars May 05 - A heated sidewalk system of coils inside the concrete will melt snow and ice in front of the tower main entrance. June 05 - Employees tour through future first-floor community room. July 05 - Landscaping, installing curbs and paving continue in front of the tower. Aug. 05 - Day Surgery patient recovery bays
   

Sept. 05 - The Northwest Tower on an early September afternoon.

   